Welsh Water Update – 28 March 2024

Welsh Water Update – 28 March 2024

Please see the update below on the next phase of work on Broad Street and Newport Street, commencing on 14th April 2024.

Broad Street is now fully reopen to traffic.

SUNDAY 14TH APRIL from 9.00am:

Broad Street and Newport Street will be closed to all traffic, for exploratory work, from outside the Three Tuns to just below Wyeford Road. Traffic from Clyro crossing Hay Bridge will be able to turn right into Broad Street and vice versa.

There will be a diversion route to Newport Street for light vehicles only via Clifford. This route will be manned to prevent unauthorised use by HGVs etc.

Heol-y-Dwr will be closed to all vehicles from the junction with Brook Street to outside The Globe.

Nantyglasdwr Lane will be closed to all vehicles at the junction with Newport Street, access to Nantyglasdwr Lane, for residents only, will be from the Hardwicke Road.

MONDAY 22nd APRIL to SUNDAY 12th MAY:

Broad Street and Newport Street will be closed to all traffic, Monday to Sunday from 1pm to 8pm, from outside the Three Tuns to just below Wyeford Road.

Traffic from Clyro crossing Hay Bridge will be able to turn right into Broad Street and vice versa.

There will be a diversion route to Newport Street each day between 1pm and 8pm, for light vehicles, only via Clifford. This route will be manned to prevent unauthorised use by HGVs etc.

Heol-y-Dwr will be closed to all vehicles from the junction with Brook Street to outside The Globe.

Nantyglasdwr Lane will be closed to all vehicles at the junction with Newport Street each day from 1pm to 8pm. Access to Nantyglasdwr Lane, for residents only, will be from the Hardwicke Road.

Outside of this time, from 8pm to 1pm, there will be single file traffic along this stretch of Broad Street and Newport Street, controlled by traffic lights.

MONDAY 10th JUNE to the beginning of JULY:

The same as above to complete this phase of the work.

JULY:

The junction of Bridge Street and Broad Street will have restricted access to allow Welsh Water to connect the two sections of pipe. The work is expected to take 1 week. Further details to follow.

COMMISSIONING WORK:

Once the work is completed there will be a number of rolling short-term closures to enable Welsh Water to test, cleanse and commission the new pipework, Further details to follow.